Ratlam nimach chittorgarh #Electrification & Doubling Update on 13-jun-19
* Doubling Update
1. chittor to shambhupura 100% completed
2. shambhupura to nimbahera
...
more... Earth work 90% complete bridge work 60% complete traking singling work 75%
3. nimbahera to nimach
earth work 70% complete bridge work 10% complete traking singling work 5% complete
* Electrification
1. Ratlam to Jaora
#crs complete
2. Jaora to Kachnara Road 95 % complete with wiring
3. kachnara road to mandsore
Foundation & poles work 98 % complete wiring work pending
3. mandsore to nimach
foundation work complete poles & clipping work 65% complete
wiring work due
4. nimach to chittor
foundation work 80 % complete poles work 30% complete clipping & wirring work due
almost 65% complete
kota chanderia eletricfication
1 kota to bundi foundation work 85% complete poles clipping & wiring work due
2. bundi to chanderia no work