#PuneSolapurGulbargaDoubling
Yesterday, I have traveled from Pune to Solapur. PFB updates of doubling between Bhigwan and Bhalawani.
Section - Work completed in %
1. Bhigwan to Jinti Road - 30
Leveling - 20%
Rock...
more... cutting - 70%
Bridge work - 0%
2. Jinti Road to Parewadi - 40
Leveling - 40%
Rock cutting - 90%
Bridge work - 0%
3. Parewadi to Washimbe - 40
Leveling - 40%
Rock cutting - 70%
Bridge work - 0%
4. Washimbe to Pophlaj - 70
Leveling - 80%
Rock cutting - 90%
Bridge work - 10%
Track laid - 20%
5. Pophlaj to Jeur - Status Unknown
6. Jeur to Bhalawani - 95
Track laid - 100%
click herePC - RVNL
Video Credits - Self