no its not but its in working condition
ALD phaphamau doubling electrification work is 40% done
phaphamau janghai is single line electric but now in this budget this track is going to be double electrified
janghai suriawa work is 80% done
suriawa...
more... bhadohi is double electric
bhadohi sewapuri work is almost 70% done
sewapuri varanasi is double electric line
varanasi mughalsarai is double electric and now in budget 3rd line sanction