Erode-Karur-Tiruchirapalli Electrification updates
KARUR to TIRUCHIRAPPALLI (As on 29.07.2017)
At KRR Jn, Civil works for Catenary masts are in progress. Ground level construction work is going on,
on the site for Tower Wagon Shed.
RE...
more... Work between KRR-TPJ appears to be quick when compared with KRR-ED stretch.
KM 66.5 upto 103.5 (KRR-KLT) in ED-KRR-TPJ section: Wired. Still wiring required at stns. like VRQ, LP.
KM 103.5 to 106.5 KM in ED-TPJ sec : Kulithalai station is being readied for wiring.
KM 106.5 to 117 in ED-TPJ sec: : Wiring done.
KM 118 to 130 in ED-TPJ sec: : Masts dropped into pits and civil works to be completed.
Jeeyapuram Stn.: Only remaining Semaphore signals here in this section are to be replaced.
KM 130 to 140 in ED-TPJ sec: Work in progress upto 133 KM as on 29.07.17. Hope to touch TPJ in the coming days.
===============================
ERODE to KARUR: (As on 16.07.2017)
KM 18 to 64 in ED-KRR stretch: Catenary poles commissioned upto Pasur. Civil Work in progress @ Pugalur, Kodumudi and Pasur. No wiring when i visited
KM 0 to 18 in ED-KRR sec: Earth and concrete foundation work was pending b/w 1 Km & 7Km. In the stretch b/w KM 7 & 18,
work is in progress.