Updates on JBP-KTE electrification as on 24/12/2017.
Train - 22182 NZM SUP Exp.
{Mainly focus on the updates of JBP yard}
1. The work is at slow pace from Katni jn. to Sihora. Hole work is almost done.
2....
more... From SHR to JBP work is going on with great pace you can see poles and OHE wiring is also done and tightened (except in some patches including stations).
3. At JBP yard work is going on with great pace, placing of horizontal masts is left in few patches.
Finally at JBP station work is going on with great pace wiring is tightened and done in platform 1,2,3,4 and wiring still needs to bee tightened in platform 5 and 6.
By this pace i think PPI-JBP section will be completed by the 1st week of January 2K18 and CRS will be called in the second week of the January.
JBP-KTE will be completed at the end of March 2K18