Latest survey
●Pakur Tilbita Kotalpukur Gumani Pole Erected with catenery and wiring
● Gumani Bonidanga link cabin only pole erected
●Bonidanga link cabin to Barharwa Jn (Excluding Bhw Station) -Bonidanga hole made
●Bonidanga Link...
more... to Tildanga Hole and somewhere Pole had been erected(Bridge work and Unmanned Crossing/Limited Height Subway work are being done)
●Tildanga to Kedarnath Bridge (New Farakka south Cabin)
Pole had been erected.
●Work for making hole had been started from 09/02/2018
Near New Farakka(Excluding New Farakka Junction) Jn Both south end north.
●Farakka Barrage (No work)
●Farakka Barrage End to Jamirghata pole erected
●Sub-Sectioning and Paralleling Post (SSP)is being constructed at Khaltipur Station in which Guard wall had been made but no Transformer had been installed
●Jamirghata to Malda Town Rathbari Flyover Pole Erected with Catenery and Wire
●Malda Town station work excluding Platform Hole making work had been started since January 2018.
●Recently from 09th February Hole are being at Malda Town station All Platform (Excluding PF1)
●Malda Town Station to NimaiSarai (Mahananda Bridge) hole and pole are being erected with full pace
●Lastly It enters the Old Malda Section which has already been electrified.
Main issue is Farakka Barrage till now NOC hadn't been provided by Ministry of Water Resources River Development &Ganga Rejuvenation to Ministry of Railway as daily Gate Work is being done by Head Works Division (Farakka Barrage Project).
Lets see what happens work is going on with full swing
New DRM had also been appointed in Malda Division.