SWR targets for commissioning of sections in FY 2019-20
Newline
1.Gangavath- karatagi =27.5km part of Ginigera Raichur new line target by Dec 2019 (likely to miss).
2.Baiyappanahalli's 3rd terminal target was July 2019 missed new target is march 2020.
Doubling...
more...
1.mulvad-jumnal =17km target was July 2019 missed new target likely to be Nov 2019.
2.Lachyan -Hotgi jn =33km target is Nov 2019
3. karadi -Ammasandra =17 target is Feb 2020
4.DVG -HRR =13km target was may 2019 missed new target is Nov 2019
5. Tolahunase -DVG =9km target is Feb 2020
6.HRR - Devaragudda =31km target is Jan 2020
7.YNK-Doddaballapura =21km target Nov 2019
8. Doddaballapura-Makalidurga =15km target Dec 2019
9.Ghattaprabha-chikkodi Rd=15km target was June 2019 new target likely to be Nov 2019