Hello friends I recently travelled on the DD - MMR section.Following are my observations.
1.Bhima river bridge work near Daund about 80% complete.
2.Absolutely...
more... no work between Daund and Kashti.
3.Earth work complete between Kashti and Shrigonda.
4.Earth work complete between Srigonda and Belwandi.Track laying has started.
5.Track laid between Belwandi and Visapur...100 % work complete.
6.Sub grade work of land levelling complete between Visapur and Akolner.
7.No progress between Akolner and Padhegaon.Only land levelled between Rahuri and Vambori.
8.Track laid between Padhegaon and Belapur..100% complete.
9.Ballast and track laying between Belapur and Puntamba.The bridge work on Godavari has started.
10.Track laid between Kopargaon and Kanhegaon...100%.
11.Double line and electrification totally complete from Kopargaon to Manmsd.
12.Re - development of Ahmednagar and Kopargaon station taking place.Nagar will get total 4 platforms while Kopargaon will get 3rd platform.
Quarters behind Platform no 2 in Nagar have been demolished on June 13th 2022.
U can see Google Earth for latest updates.
Daund - Manmad doubling and electrification is only 35% complete.Will be completed by 2026.