Expenditure till date- ₹ 3759.40 Cr.
🟠Funding- CR & State govt- 50:50%
🟢Overall Physical Progress- 80%
🔘Length- 261.25 Km
🔘Land acquisition completed- 1806.19/1821.65 Hectare (99.15%)
A) Completed section-
Ahmednagar to Ashti (66.18 km)
B) Near completion section-
(Likely completion this Fin. Year).
Ashti to Eganwadi (67.12 km)
C) In progress-
Eganwadi to Parli.
🟢In Progress Works-
☑Earthwork - 419.88/430.43 Lcum (97%)
☑Important bridges /Major Bridge - 58/64 (91%)
☑Minor Bridges- 301/252 (84%)
☑Ballast supply - 6.603/7.52 Lcum (88%)
☑ROB/RUB- 128/195 (66%)
☑Station Building- 6/21 (30%)
☑Signaling and telecom works- 10 stations in progress
☑ Track Linking – 124.32/285.89 track km (43%)
☑ Power line crossing – 568/626 (91%)
☑Electrification- 261.25 km in progress.
🔴Completion of this new line will improve connectivity of Marathwada region.
🔘Progress of doubling/3rd/4th new lines all over Central Railway’s 5 divisions-
🔘CR has completed 161.80 km multitracking (new line/doubling/3rd/4th line) in current FY from April 2023 till date 2023.
🔘3890 Crs planned by CR in this year for new lines/doubling/3rd/4th line.
🔘2990 Crs expenditure done till date.