#PuneMirajDoublingProject тЧП PART : PUNE TO SATARA тЧП
тЧП Pune to Shindawane (31KM) FEDL
тЧП Shindawane to Ambale (10KM)
Shindawane Ghat Doubling
Bridge no 35/1 :- Pillar work done, Span work still pending
Tunnel No 1(Dn Line) :- Boring done, Ground leveling work in progress
Bridge No 36/1 and 36/2 :- Fully done, Track Laying and Pole erection not done yet
Bridge no 37/1 :- Foundation work started
Bridge No 37/2 and 37/3 :- No Work
Bridge No 38/1 :- Pillar work done, Span work still pending
Ground Leveling almost done
Some poles are erected
Partially wiring and bracketing done from Shindawane outer to some distance
тЧП Ambale to Wathar (78 KM) FEDL
тЧП Wathar to Palsi (9 KM)
Ground Leveling and pole foundation work in progress
Ground leveling work yet to start at some points
тЧП Palsi to Jarandeshwar (9 KM) FEDL
тЧП Jarandeshwar to Satara (8 KM)
Subgrade Work, Rock Cutting work, and Minor Bridges work in progress
Blanketing ballast has arrived at some points
Total Doubled Line :- 118 KM
Under Doubling :- 27 KM
Source :- YouTube channel : KD Travel Studio
Attaching Vdos of the same under this post