#PuneMirajDoublingProject ● PART : PUNE TO SATARA ●
● Pune to Shindawane (31KM) FEDL
● Shindawane to Ambale (10KM)
Shindawane Ghat Doubling
Bridge no 35/1 :- Pillar work done, Span work still pending
Tunnel No 1(Dn Line) :- Boring done, Ground leveling work in progress
Bridge No 36/1 and 36/2 :- Fully done, Track Laying and Pole erection not done yet
Bridge no 37/1 :- Foundation work started
Bridge No 37/2 and 37/3 :- No Work
Bridge No 38/1 :- Pillar work done, Span work still pending
Ground Leveling almost done
Some poles are erected
Partially wiring and bracketing done from Shindawane outer to some distance
● Ambale to Wathar (78 KM) FEDL
● Wathar to Palsi (9 KM)
Ground Leveling and pole foundation work in progress
Ground leveling work yet to start at some points
● Palsi to Jarandeshwar (9 KM) FEDL
● Jarandeshwar to Satara (8 KM)
Subgrade Work, Rock Cutting work, and Minor Bridges work in progress
Blanketing ballast has arrived at some points
Total Doubled Line :- 118 KM
Under Doubling :- 27 KM
Source :- YouTube channel : KD Travel Studio
Attaching Vdos of the same under this post