💥Thokur-Bijoor CRS inspection completed
💥Bijoor-Kumta completed.CRS Inspection Soon
💥Kumta-Anokla Pole erection completed
💥Anokla-Karwar pole erection on progress.Poles erected at Karwar Station
💥Karwar-Mao pole erection on progress.Poles Erected at Balli
💥Mao...
more... outer-Verna Pole erection completed.grouting work on progress
💥Verna-Ratanagiri Pole erection completed.But Hard rock location and cutting area is left
💥Ratanagiri-Veer Outer Wiring completed
💥Veer-Roha Pole erection progress
Verna-Kumta Targeted to complete on March 2021
Verna-RN Targeted to complete on May 2021 (Mostly complete on Dec 2021
RN-Roha Targeted to complete on Dec 2020
#konkanelectrification