#RVNL says that starting from August-Nov 2015, the
#Electrification of Rajpura-Patiala-Dhuri-Lehra Mohabat shall take 2 and a half years to complete. So, that is surely going to Jump the TDC of March 2016. Says, official formalities taking time, but you'll start to see the camp offices on this section by August 2015, with trenching and OHE Mast erection. Tenders are ready to be floated / uploaded/ published/. May see them in a month or so.