Process of casting Foundation for Railway electric pole.
Electrification update of Guntakal - Ballary 50km route.
1. Foundation work for Railway electric pole - 70% work completed
2. Installing electric pole in foundation - 30% work completed from Guntakal end.
3....
more... Installing OHE electric wire - work yet to be start.
@00:10 - Excavation for foundation of electric pole of appropriate size and
Material shifting process is going on.
@00:22 - Preparing base for electric pole mouldes.
@01:19 - Installing electric pole mouldes under the guidence of Engineer.
@02:58 - Casting concrete around the mouldes under the guidence of Engineer.
@03:20 - Foundation work is completed. Wait till initial setting time for removing mouldes.
@03:41 - Removing process of electric pole mouldes after initial setting time (90min).
@05:26 - Foundation is ready. After 28 days of curing electric pole can be install in this foundation.