It was a very important project and had High Priority status. 90% land was acquired, 20% work was also completed.
But this project had a clause that land loosers will get railway job as per their knowledge. According to that some got jobs also. But later suddenly Railway Board stopped further Recruitment, and then locals started protesting and stopped project work. When SER had written several letters to Railway board on this issue and had asked for RB reply on this. Railway Board didn't reply SER letters and nor took any initiative on this. As a result this project had to be Stopped and later Closed by RB and SER.