Blog Entry# 4815787
Posted: Dec 18 2020 (08:40)
48 Responses
Last Response: Jan 25 2021 (12:02)
Crs schedule Release
1.Det to Udaipur #Eletricfication
2. Raigadh to Dungarpur #GC
Det to udaipur crs today morning 10.30
Next day Raigadh to Dungarpur 19 Dec 25 km crs.
Next...
more... 20 & 21dec 21-21km crs.
Udaipur Ahemdabad
#Eletricfication work start next month