5. Electrification works in progress
Electrification works in Progress
CORE Project
Section
RKM...
more...
Energised till 31.3.12
Balance RKM As on 1.4.12
Ambala
Moradabad-Rosa
169
169
0
Khurja-Meerutt City-Saharanpur
200
200
0
Ghaziabad-Meerutt
47
47
0
Ghaziabad-Moradabad
140
0
140
Jallandhar-Jammutawi-Udhampur
275
178
97
Udhampur-Katra
25
0
25
Katra-Dharam
72
0
72
Sakurbasti-Rohtak
60
60
0
Rohtak-Bhatinda-Lehra Mohabbat
252
0
252
Bhubaneswar
Vizianagaram-Rayagada-Titlagarh
263
0
263
Titlagarh -Sambhalpur-Jharsuguda incl.IB Bypass line
238
0
238
Pandabeswar-Sainthia-Pakur incl. Khana-Sainthia
205
19
186
Andal-Sitarampur via Jamuria - Ikhra
57
0
57
Lucknow
Rosa-Lucknow-Alamnagar-Utratia
179
179
0
Mughalsarai-Sultanpur-Utratia
296
296
0
Varanasi-Lohta-Janghai-Phaphamau-Unchahar incl. Phaphamau-Prayag-Allahabad
207
49
158
Rosa-Sitapur-Burhwal
181
0
181
Gorakhpur
Barabanki-Gorakhpur-Chhapra Kachehariincl. Thawe-Siwan
452
256
196
Hajipur
Chhapra Kachehari -Barauni**
305
274
31
Barauni-Katihar
187
42
145
Garwa Road-Chopan-Singrauli
257
0
257
New Jalpaigudi
Katihar-Guwahati incl. Katihar-Barsoi
649
31
618
Pakur-Kumedpur incl. Malda-Singhabad
153
0
153
Chennai
Bangalore suburban area
53
45
8
Trivandrum-Kanyakumari
87
87
0
Madurai-Tuticorin-Nagercoil
262
256
6
Vellore Cantt.-Villupuram
150
140
10
Shoranur-Mangalore-Penambur
328
0
328
Coimbatore -Mettupalayam
33
0
33
Secunderabad
Lingampalli-Wadi
161
149
12
Gondia-Ballarshah
250
0
250
Kengeri-Mysore
125
30
95
Nallapadu- Guntakal
426
0
426
Kota
Ujjain-Indore incl. Deaws-Maksi
115
115
0
Kanpur-Jhansi
240
202
38
Mathura-Alwar-Rewari
203
0
203
Cheoki-Manikpur-Itarsi incl. Satna-Rewa
653
0
653
TOTAL
7955
2824
5131
RE Works with RVNL
Nandalur-Guntakal
222
180
42
Hospet-Guntakal & Torangallu – Ranjitpura
138
0
138
Obulavripalle-Krishnapatnam
113
28
85
Bharauch-Samni-Dahej
62
62
0
Haridaspur-Paradeep
82
0
82
Tomka-Jharoli
151
151
0
Angul-Sukinda
99
0
99
Amla - Chhindwara- Kalumna
257
0
257
Pune-Wadi-Guntakal
641
0
641
Daund-Manmad incl. Puntamba-Sirdi
255
100
155
Valupada-Iddapalli
9
9
0
Yelahanka-Dharmavaram-Gooty
306
0
306
Titlagarh-Raipur
202
0
202
Manheru-Hisar
74
0
74
Total
2611
530
2081
RE Works with Zonal Railways
Chandigarh-Ludhiana (NR)
112
43
69
Noli-Shahdara (NR)
10
0
10
Laksar-Haridwar-Raiwala-Dehradun (NR)
79
0
79
Bardhman-Katwa (ER)
52
24
28
Tamluk-Digha (SER)
94
89
5
Shantipur-Krishnanagar-Nabadwip (ER)
27
13
14
Rewari-Manheru (NWR)
69
0
69
Angul-Sambhalpur (ECoR)
156
0
156
Miyagam-Karjan-Dabhoi-Samlaya (WR)
96
0
96
Vijayavada-Gudivada-Bhimavaram- Narsapur-Gudivada-Machilipatnam and Bhimavaram-Narsapur (SCR)
221
0
221
TOTAL
916
169
747
IRCON
Dharam-Baramula
195
0
195
GRAND TOTAL
11677
3523
8154
** Ganga Bridge line (28 RKM) being done by ECR.
status as on march 31-2012