With final test runs almost complete, Mumbai Monorail's first phase will take on commuters before the festive season, say MMRDA officials.
.
Slowly but steadily, the Mumbai Monorail is getting ready to open its doors to citizens before Diwali. Trial run between Chembur and Wadala would be completed by mid-July.
.
After...
more... the first trial run the MMRDA approached Indian Railway of testing and certify the safety measures which was declined by Commissioner of Railway Safety (CRS) stating that it does not have capacity to certify the monorail, as they have no expertise or knowledge in running monorail. Then MMRDA appointed a Singapore-based SMART agency to monitor the testing process which is undergoing now.