Defying Daunting Terrain, Linking Sikkim!
Sivok-Rangpo Rail Line ProjectЁЯЪЙ
Progress (As on 28.02.2023):
ЁЯУИOverall...
more... Physical Progress: 53.2%
ЁЯкиTunnel Mining works: 27.16 km
ЁЯПЧя╕ПPiling work: 20111 m
ЁЯПЧя╕ПPier work: 526 m
ЁЯПЧя╕ПEarthwork: 5.5Lcum
ЁЯМЙMinor Bridge-5 nos