💰 Cost- ₹ 3445.48 Cr
💰 Expenditure till date- ₹ 1910.07 Cr.
🟢Overall Physical Progress- 47%
🔘Length- 270 Km.
🔘Land acquisition completed- 1911/2138 Hectare (89%)
🟢In Progress Works-
☑Earthwork - 87.54/201.14 Lcum (44%)
☑Formation - 40/284.60 km
☑Major Bridges- 32/80
☑Minor Bridges- 50/320
☑Road over bridge (ROB) - 43 In Progress
☑RUB/LHS– 19/52 in progress
☑Station Building- 3/27
☑Tunnels– 6 in progress of total 8 km length
☑ Track Linking- 28/284.60 track km
🔴Completion of this new line will improve connectivity of Vidarbha and Marathwada region.
🔘Progress of doubling/3rd/4th new lines all over Central Railway’s 5 divisions-
🔘CR has completed 161.80 km multitracking (new line/doubling/3rd/4th line) in current FY from April 2023 till date 2023.
🔘3890 Crs planned by CR in this year for new lines/doubling/3rd/4th line.
🔘2990 Crs expenditure done till date.