CHENNAI (Metro Rail News): Under Phase-2 of Chennai Metro which will consist of three corridors of total route length of 118.9 km, there will be three...
Delhi (Metro Rail News): In line with its vision to improve the quality of life of people, NCRTC has signed MoU with SECI (Solar Energy Corporation...
Work is progressing at rapid pace for Agra Metro, so far work on 480 piles, 71 pile capes and 31 pillars is completed for the elevated...
Phase-2 of Chennai Metro comprises construction of three lines covering 118.9 km to be built at a cost of INR 61,843 crores with all three corridors...
As the first pile foundation was started for constructing viaducts between Vadodara and Ahmedabad, the NHSRCL team stands proudly alongside the machine, knowing that they are...